Major projects

Tallington Segment Manufacturing Facility

Tallington Segment Manufacturing Facility

Creating concrete segments for the Thames Tideway project

Leabrand provided both technical and skilled workforce to produce concrete segments using a Static Mould pouring system. 

Avonmouth Segment Manufacturing Facility

Avonmouth Segment Manufacturing Facility

Constructing concrete segments for the cooling tunnels which is part of the Hinckley Point C Nuclear Power Station

Leabrand provided both skilled and technical resources to produce in excess of 35,000 concrete segments to Nuclear standards using a automated carousel system operating two shifts over a 24 hours basis.

Crossrail C610 Systemwide

Crossrail C610 Systemwide

Provided over 350 personnel in all disciplines including safety critical.

Installing high speed track and associated works from Plumstead to Westbourne Park. Slab track works completed ahead of schedule. As well as concrete slab track works, the associated specialist works included Overhead lines, Derailment containment, Mechanical and Electrical works and safety critical activities associated with the rail industry. Works are still on going on this project.

Long Marston

Long Marston

The contract was for the design, construction and testing of an innovative Low Impact Light Urban Rail system.

The construction of 100 meter rail system was to be completed on an existing test road section. The completed Low Impact Light Urban rail was instrumented and then tested for a 4 week period by Cambridge Centre for Smart Infrastructure and Construction (CSIC).

Crossrail C305 Dragados Sisk Joint Venture

Crossrail C305 Dragados Sisk Joint Venture

Setting up a concrete segment manufacturing facility. Producing in excess of 108,000+ concrete segments to be used on the Central Section of the Crossrail project. Using a twin carousel system over a 24 hour period. Works included manufacturing, storing and transportation by barge from Chatham to various sites in London for the central section of the Crossrail tunnels.

Tilbury Loop Project

Tilbury Loop Project

Extending 12 Nr stations along the C2C Route including supplying all Civils Trades, PTS staff including safety critical.

Belvedere waste-to-energy facility

Belvedere waste-to-energy facility

Setting up precast yard, form work steel fixing and concrete placing to manufacture pre-cast concrete units which were then transported by Barge and fixed in situ and concrete works carried out to construct new jetty for Costain Marine.

Olympics Village Bridge

Olympics Village Bridge

Carried out groundworks including pile breakdown, formwork, reinforcement and concrete placing to construct new bridge over live railway lines joining Olympic stadium to Westfield’s shopping centre.

A2/A282 bridge construction and road widening for Costain

A2/A282 bridge construction and road widening for Costain

Supplying in excess of 120 personnel in all trades.

DLR Woolwich Arsenal extension

DLR Woolwich Arsenal extension

Formwork, reinforcement, concrete placing and finishing of concrete tracks in both tunnels.

“I would be more than happy to recommend Leabrand for any future works,”

Christopher Chassagnette, Colas Rail, project manager.

DRL 3 Car Project

DRL 3 Car Project

Extending Existing Platforms to take 3 cars instead of 2 works including diamond drilling, percussion drilling, resin anchoring, pull out testing, formwork, reinforcement, concrete placing, track installation and associated works.

Channel Tunnel Rail Link

Channel Tunnel Rail Link

250 + personnel installing high-speed track and associated works for 45 kilometres between Swanscombe, Kent, and St Pancras.

Completed six months ahead of schedule.

“They did a very good job for us, overcoming lots of difficulties without making a fuss,” - Mike Casebourne, ACT, project director.

M2 Bridge, major civil engineering project

M2 Bridge, major civil engineering project

Staff provided across the entire development for Costain / Skanska / Mowlem.